At times, I'm seeing some inconsistencies with sql server agent's value in the sysjobschedules.next_run_date and time fields.
I have a web interface that interacts with the sql scheduling system.
I've created a test job that started on March 16th 2011 at 9:45am. I've set it up to happen every 4 weeks on a Wednesday.
From today, this should put a next run date and time on January 18th at 9:45 but the Next Run Date/Time value for my job is saying January 4th.
The values in the job properties look good.
The start date says March 16th 2011.
The frequency values are all correct.
But it seems SQL is failing to land this occurrence properly.
Here is some relevant info for the job in question from the sp_help_jobschedule proc
freq_type 8
freq_interval 8
freq_subday_type 1
freq_subday_interval 1
freq_relative_interval 0
freq_recurrence_factor 4
active_start_date 20110316
active_end_date 99991231
active_start_time 154500
active_end_time 55959
date_created 2011-12-29 20:37:05.737
schedule_description Every 4 week(s) on Wednesday at 154500
next_run_date 20120104
next_run_time 154500
if the start date is March 16 2011 at 9:45, it doesn't make sense that the next run date would fall on January 4th 2012 based on the properties of the job.
I guess my question is, how much can I rely on this Next Run Date data?