0
votes
1answer
156 views

Creating a job scheduled based on a specific timezone

I have an Oracle database hosted in Europe. I need to create a scheduled job in the database to send email. I need to send email daily at 17:30:00 in India standard time (IST). I know how to send ...
2
votes
2answers
836 views

DBMS_SCHEDULER event schedule jobs not executed when triggered almost at the same time

I moved this question from stackoverflow to here as it was marked on hold as off-topic. On Oracle 10g2 DB I have set up multiple event triggered DMBS_SCHEDULER jobs and all of them are subscribed for ...
1
vote
1answer
277 views

Force chain to start immediately after completion instead of on a timer

Is it possible to force an Oracle chain to restart immediately after it finishes executing, instead of on a timer? I have only found ways to do a temporal restart, which doesn't really work for me as ...
3
votes
2answers
571 views

Disabling DBMS_SCHEDULER queue

Despite a lot of searching, I can't seem to find a solution to this problem we are having. Our system enables users to submit certain processes to be run in background while they continue working. ...