Jul 23, 2019 at 21:58 comment added HandyD Best practise would be to change replicas to Synchronous Commit, failover to a replica that won't be affected by any outage from the change, perform your change and then failback after the change once replicas are synchronised, and finally reset any Asynchronous replicas that were changed to Synchronous.
Jul 23, 2019 at 18:36 vote accept WadeH
Jul 23, 2019 at 13:11 comment added WadeH Thank you for your reply. Would this be considered the best practice in this scenario or is there something else I should consider?