I have a weekly and nightly SQL Server Agent jobs executing a weekly and nightly maintenance plans, resp.
These weekly (on Sunday) and nightly (on other 6 nights of the week) maintenance plans differ only in the 1st task from total consecutive six steps. That is, in nightly/daily maintenance plan the 1st step is "Reorganize Indexes on all User databases" and in weekly/Sunday maintenance plan the first step is "Rebuild Indexes on All User Databases".
Is it possible and how to run just one (instead of two) maintenance plan, all 7 nights of week, with condition that on 6 days the 1st step is one (Reorganize Indexes) and on the rest 1 day of week the 1st step is another (Rebuild Indexes) ?